Tehran office — Trita Tower, Floor 13 Request a quote
NAD Toseeh Paydar Request a Quote
Back to blog
Rooftop Air-Cooled Chiller Installation Checklist: Frame, Pump, Valves and Insulation
Published on October 11, 2026 · NAD Toseeh Paydar Team

Rooftop Air-Cooled Chiller Installation Checklist: Frame, Pump, Valves and Insulation

Installing an air-cooled chiller on a roof is more than lifting the unit into place; structure, airflow, water and power must be coordinated. This checklist is written for owners, supervisors and contractors to review before work and at handover. Every project has its own requirements and the consultant's working drawings take precedence.

1. Structure and supports

Check the operating weight (with water inside) and crane lifting with the structural engineer from the start. Mount the chiller on a level steel frame or concrete plinths with vibration isolators so vibration does not reach the building. The frame should sit above the roof surface so the area below can be cleaned and rain does not collect.

2. Air clearance and orientation

An air-cooled chiller needs fresh air. Do not box in the sides or top with walls, parapets or other equipment, or hot air recirculates and capacity drops. Take the required clearances from the manufacturer's data sheet. Prevailing wind and direct sun also matter when choosing the location.

3. Pump, expansion vessel and buffer tank

Select the circulation pump for the calculated flow and head, and consider a standby pump on critical projects. The expansion vessel absorbs water volume changes with temperature and must be installed in the correct place in the loop. A buffer tank prevents frequent compressor cycling on chillers that run at low load.

4. Valves, strainers and instruments

  • Isolation valves at chiller inlet and outlet and around the pump so service does not require draining the whole loop
  • Strainers before the pump and chiller inlet to protect the heat exchanger
  • A check valve after the pump
  • Pressure gauges and thermometers at inlet and outlet to record conditions at handover
  • Flexible connections to isolate pipe vibration
  • Air vents at high points and drain valves at low points

5. Insulation and pipe cladding

Chilled-water pipes need suitable insulation with a vapour barrier and weather cladding to prevent condensation and energy loss. On a roof, aluminium or galvanised cladding over the insulation is usual. Insulate pipe ends and valve areas so that service stays possible.

6. Freeze protection

Where winter temperatures fall below zero, either use antifreeze (glycol) at a suitable percentage or drain and protect the loop in winter. Glycol percentage affects capacity and pressure drop and must be allowed for in pump and chiller selection.

7. Power and controls

Run the supply cabling, a local disconnect, phase protection and earthing to the manufacturer's specification. Coordinate the pump control panel with the designer; see the electrical panels page. If the chiller will connect to a BMS, fix the communication protocol from the start.

8. Commissioning and handover

Before start-up, flush, fill and vent the loop and pressure test. At handover record compressor current, water inlet and outlet temperatures and pressures, and get operator training. For information needed before a quote, see the chiller quotation checklist, and see rooftop examples in the installation gallery.